I would like very much to donate so that I can test version 2. What is a minimum donation? I ask only because my company cut our pay severely starting last month. Fortunately, I was able to use my Klok data to show that they shouldn’t furlough me as they have with several of my colleagues who couldn’t account for how their time had been spent last year. Thank you so much for Klok in that regard. Hopefully times will get better or I will get a job with a better company soon.
rafaelad89ParticipantI’ve accidentally figured out how to get to old time sheet data. It happened when I tried to arrow back from January 2010 monthly timesheet view to December 2009 and had nothing showing for any months before January. So, while in “Week View”, I clicked on “select a week” icon and picked a week in the middle of December. When I clicked on “monthly timesheet”, there was all the month’s data for December. By selecting a week in the middle of the month of interest, I was able to get my month’s data.
I hope this helps someone,
RonP.S. Hopefully in the next version, all the times in the start and stop fields will be rounded up to the nearest minute. I found that if I start and stop several projects during the day, I can be missing several minutes from my time. For now, I go back if I see a gap between tasks and fix the times.
rafaelad89ParticipantI’ve accidentally figured out how to get to old time sheet data. It happened when I tried to arrow back from January 2010 monthly timesheet view to December 2009 and had nothing showing for any months before January. So, while in “Week View”, I clicked on “select a week” icon and picked a week in the middle of December. When I clicked on “monthly timesheet”, there was all the month’s data for December. By selecting a week in the middle of the month of interest, I was able to get my month’s data.
I hope this helps someone,
RonP.S. Hopefully in the next version, all the times in the start and stop fields will be rounded up to the nearest minute. I found that if I start and stop several projects during the day, I can be missing several minutes from my time. For now, I go back if I see a gap between tasks and fix the times.
rafaelad89ParticipantI’m using Klok 1.5.1 RC 1.1. When I click on “monthly timesheet”, I get the current month’s data which includes all projects. When I then click ‘previous’, all previous months have 0 for each day. When I click ‘next’ to get back to the current month, it now has all 0’s for data. If I close that timesheet window and open it back up, the current month shows its data again.
I’ve filed a bug report but need to get last month’s data.
rafaelad89ParticipantI’ve been using Klok 1.5 RC 1.1 since the beginning of August and have had this problem happen but it is random in occurrence. One day’s worth of tasks are stacked on top of the each other when I close the app. When I start Klok the next day, the previous day’s tasks are suddenly cascaded. Making sure that there is at least a minute between tasks doesn’t fix this appearance.
Just thought I’d pass this along. Klok is a great app otherwise!